MTDC pushes Naagoashi resort back to early 2028, its third target this year
Maldives Tourism Development Corporation now expects its HDh. Naagoashi resort to be finished in the first quarter of 2028, after targeting April 2027 and then October 2027 earlier this year. The government's construction-period extension runs out on 20 November 2026.
Maldives Tourism Development Corporation (MTDC) now expects its resort at HDh. Naagoashi to be finished in the first quarter of 2028. That is the third completion target the listed company has given in its quarterly reports this year. In April it said 30 April 2027. In July it said the resort would open in October 2027. Its third-quarter report, filed with the Capital Market Development Authority (CMDA) on 2 November 2026, moves the date back by at least another three months.
The government owns 45.94% of MTDC's shares and the public holds the rest, according to the same report. The company has held the lease on Naagoashi since 17 September 2006. A previous sublessee left the resort about 40% built. MTDC took the project back in 2023 to develop it itself as a five-star resort, and it secured a mobilisation permit from the tourism ministry on 18 March 2025.
How the target has moved
| Filing | Date filed | Target given | What MTDC reported |
|---|---|---|---|
| Fourth-quarter report, 2025 | 28 January 2026 | Full-scale construction to start in Q1 2026 | Project management consultant chosen in October 2025; surveys and site preparation under way |
| First-quarter report, 2026 | 30 April 2026 | Completion 30 April 2027, as advised by the consultant | Mock-up rooms delayed by material shortages and quality concerns; surveys show dredging is needed to bring in heavy equipment |
| Second-quarter report, 2026 | 30 July 2026 | Resort opening October 2027 | International deliveries of materials delayed by "the regional conflict in the Middle East" |
| Third-quarter report, 2026 | 2 November 2026 | Completion in the first quarter of 2028 | Mock-up room about 95% complete; main civil works not yet started |
Source: MTDC quarterly reports filed with the CMDA.
What the third-quarter report says
The latest report gives no single cause for the new date. It says the Q1 2028 target depends on "the timely commencement and progression of the remaining construction works and associated approvals". Mobilisation is complete, but the company describes the project team as still "working towards commencing the next phase of construction".
Work on the water villas is on hold until engineers decide whether the existing piles can be repaired, reused or must be replaced. MTDC says the aim is to keep construction costs down. The company is also still working through requirements from the Environmental Impact Assessment and getting technical advice on coastal changes needed for the next stage.
MTDC has not published the resort's total budget, its number of villas or the name of a main building contractor in any of the 2026 reports. Its 2025 annual report says the board approved a construction management plan and a budget for "Phase 1" of the project, but it gives no figure.
Paying for it
The quarterly accounts show MTDC is borrowing as it spends. Its term loan stood at USD 3.02 million at the end of March 2026 and rose to USD 6.18 million by 30 September, after the company drew a further USD 3.16 million in the third quarter. The reports do not name the lender or say what the loan is for. Spending on property, plant and equipment came to USD 4.19 million in the first nine months of 2026, by our calculation from the three cash-flow statements. That figure also covers MTDC's new ten-storey office building in Hulhumalé, which the company said was due to open on 1 November 2026.
The company's board approved in principle a rights issue, a sale of new shares to existing shareholders, in the fourth quarter of 2025. In its third-quarter report MTDC says delays in that process held up its 2025 annual general meeting. The meeting finally took place on 31 August 2026. MTDC paid a fine of MVR 100,000 for holding it after the deadline set by the Maldives Stock Exchange listing rules.
MTDC's income
MTDC's revenue comes from subleasing two operating resorts: Kihavah Huravalhi in Baa Atoll, run as Anantara Kihavah since December 2010, and Magudhuvaa in Gaafu Dhaalu Atoll, run as Ayada Maldives since November 2011. Revenue for July to September 2026 was USD 1.23 million and profit was USD 151,079. In the second quarter the figures were USD 1.25 million and USD 125,755.
The company lost its income from Naagoashi when that sublease ended. Its 2025 annual report blames "discontinuation of Hdh. Naagoashi Sublease" for a 1.86% fall in revenue, to USD 5.13 million. At 30 September 2026 MTDC had USD 6.30 million in cash and total assets of USD 102.15 million. Its debt-to-equity ratio was 0.93, up from 0.84 at the end of June.
Not Haa Dhaalu's first resort
All four MTDC quarterly reports cited here describe Naagoashi as the resort that "will be the first resort to be opened in Haa Dhaalu". The government's own figures no longer support that. The Ministry of Tourism and Civil Aviation's monthly statistics for September 2026 list two operational resorts in Haa Dhaalu Atoll at the end of that month, with 162 beds between them. The atoll received 4,170 tourists at resorts, hotels and guesthouses from January to September, 0.3% of the national total.
The ministry's list of resorts under development names MTDC as the lessee of Naagoashi. It names two other Haa Dhaalu islands: Nolhivaranfaru, a training resort leased to Nalaveli Maldives, and Vaikuramuraidhoo, leased to Glamour Investments. For the wider picture of new openings, see our guide to resorts due to open in 2026 and 2027.
What happens next
MTDC's reports say the government extended Naagoashi's construction period until 20 November 2026. None of the four reports says whether MTDC has asked for a further extension. None says what would happen if the deadline passes with the resort unfinished. As of 16 November, MTDC had filed no separate disclosure on the matter with the CMDA. Its fourth-quarter report for 2026, due in early 2027, should show whether the Q1 2028 target still holds and whether the extension has been renewed.